Update on Rezone of Black Lake Quarry Site

Where we are with the petition

SSBA’s petition asking the Growth Management Hearings Board (GMHB) to overturn the rezone of the Black Lake Quarry (BLQ) mine site from a rural zone to an industrial zone is now in its final stages. The appeal is the latest chapter in SSBA/BHAS’s 25-year effort to conserve the Black River Corridor.

Our fine legal team, composed of Claudia Newman and Zak Griefen of Bricklin & Newman LLP, with support from appellants and supporters, handled the briefing and the oral arguments.  The hearing occurred July 8th. We are asking the GMHB to overturn and invalidate the Thurston County Board of County Commissioners’ 4 to 1 decision to approve the rezone. 

It is now up to the Growth Management Hearings Board to deliberate. Their final decision is to be issued by August 17, 2026.

Watch:  Black Lake Quarry appeal hearing

Read: SSBA’s reply brief and attached exhibits

Please consider donating to help defray legal costs. Click here to donate 

Our history with the Black River

This is not a new area of concern for SSBA.   SSBA/BHAS has been working to protect this major river corridor for over 25 years.  The Black River corridor is the only fully intact river system in the county, with extensive wetlands full of birds, threatened Oregon spotted frogs and Olympic mudminnows.  Its bogs contain rare plants, and the beaver dams provide havens for juvenile salmon.   These ecosystems and wildlife are the reasons why the Black River Unit of the Billy Frank Jr. Nisqually National Wildlife Refuge was established in 1996.   Much of the northern part of the corridor is in the wildlife refuge. The refuge surrounds the mine site in three directions.  

Below is a list of some of the documents from the Conservation Committee archives involving this area:

  • 2001 – Black Hills Audubon Society letter from Heath G. Packard to Thurston County
  • 2001-2007 Sue Danver leads BHAS advocacy to reduce risks to the Black River corridor
  • 2007 – Thurston County, in response to successful GMHB suit by Futurewise, created the Rural 1 house per 20 acres zone (R1/20) specifically to conserve areas like the Black River Corridor.
  • 2008-2018 – BHAS advocacy/appeals to reduce environmental risks to this area
  • 2018 – BHAS settlement agreement restricts environmentally risky uses at the mine site.
  • 2019 – Center for Natural Land Management takes over the Black River Preserve / Mima Prairie (Important Bird Area)
  • 2023 -2024- 2025 BHAS advocates  against the rezone request at the mine site.
  • 2025 September:  Thurston County Planning Commission votes 6-3 against the rezone.
  • 2025 December:   Thurston County Board of County Commissioners votes 4-1 (Comm.  Clouse opposing) to approve the rezone
  • 2026 February:  SSBA files a petition to the GMHB to overturn the rezone as a direct conflict with the land use history and protective zoning along the Black River Corridor.